Energy planning of energy-intensive public building was conducted by simulation-based MOBO tool. Work allowed guiding for procurement for the whole life cycle.
New constructions require planning and modelling for energy use, which often meet strict environmental criteria. Procuring process must meet these expectations, and here the planning was based on simulations and multi-objective optimization process for the whole life cycle of an energy-intensive building complex, including a public swimming hall. Time frame was set for 25 years. The process gave valuable support for the procurement process. Both energy consumption and LCC were evaluated for the building complex. Optimized measures focused on both energy efficiency of the building envelope and energy performance of the HVAC and building services systems. The optimization work helped city of Rauma to select cost-effective and low-energy consumption options for the separate tendering of energy efficiency systems of the building complex. Beneficiaries are city of Rauma and all tax-paying Rauma inhabitants.

Resources needed

One consultant (Granlund Ltd) was utilised for calculations. MOBO energy optimization tool (Palonen et al., 2013; developed by Aalto Univ. & VTT, Finland) was used.

Evidence of success

Several options for potential energy savings with economic savings were found through optimization process. LCA and LCC were utilised in evaluations. By selected options, 40% energy savings were obtained (214t CO2/year). By Investing into energy efficiency, 25 years’ time frame, city saves over 1,7 m€. The simulation study clearly shows, how e.g. the initial higher investment costs (for e.g. solar panels, and heat exchanger systems) result finally in diminished LC and energy costs.

Difficulties encountered

no issues

Potential for learning or transfer

The practice shows how a complex public procurement process can be greatly facilitated even for very complex environment, to meet the requirements for low energy consumption, cost-effectiveness and material efficiency. Simulations and modelling with a long period, by considering all aspects of a building life cycle as a guiding document, results in significant cost savings for the municipality, and results in beneficial environmental impacts. Political decision-making will be much easier, when LCA-based calculations are investigated. This way the decisions can be based on facts and on as accurate calculation results as possible using modern and sophisticated simulation and optimization methods, such as multi-objective optimization.
Main institution
City of Rauma
Location
Länsi-Suomi, Finland (Suomi)
Start Date
May 2019
End Date
May 2020

Contact

Pekka Maijala Please login to contact the author.